Symptom
When performing a material cost estimate in SAP S/4HANA Cloud Public Edition, there is uncertainty regarding how the exchange rate is selected and applied. Users want to understand the logic behind the process.
Environment
SAP S/4HANA Cloud Public Edition
Cause
The exchange rate used during a material cost estimate is determined based on system-specific configuration and input values such as the Conversion Date and Exchange Rate Type.
Resolution
To understand how the exchange rate is determined during a material cost estimate, the following factors should be considered:
-
Conversion Date:
- The conversion date is automatically filled with the valuation date during the material cost estimate.
-
Exchange Rate Type:
- The system determines the exchange rate type for the cost estimate using the following steps:
- Step 1: The exchange rate type is obtained from the Planning Category
PLN. This is configured in the SSCUI101970 - Maintain Category for Planning. - Step 2: If the exchange rate type cannot be determined using the Planning Category, a fallback exchange rate type P is used.
- Step 1: The exchange rate type is obtained from the Planning Category
- The system determines the exchange rate type for the cost estimate using the following steps:
Keywords
Material cost estimate, exchange rate determination, valuation date, conversion date, planning category PLN, SSCUI 101970, SAP S/4HANA Cloud Public Edition, fallback exchange rate type, cost estimate exchange rate. , KBA , CO-PC-PCP-2CL , Product Cost Planning (Public Cloud) , Problem