SAP Knowledge Base Article - Preview

3669242 - No quantity update in subsequent operations when using parallel sequences

Symptom

Confirmed quantity is not updated in subsequent operations when using parallel sequences.

Example: You have a order with Operation 0010 and 0020 with quantity 100 each. After confirming a yield of 110 in the first operation, the second operations still shows 100 as the operation quantity, even though you have the "Adjust Quantities in Order to Actual Values" set in Production Scheduling Profile (OPKP). This can lead to confusion or incorrect assumptions about progress in the routing.


Read more...

Environment

  • SAP ERP Shop Floor Control (PP-SFC)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP Enhancement package for SAP ERP
  • SAP Enhancement package for SAP ERP, version for SAP HANA
  •  SAP S/4HANA Cloud Private Edition

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Cloud Private Edition all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

parallel, sequence, operation, quantity, yield, confirmation, subsequent, sap, s/4hana, CO11N, CO11, CO03, production, order, adjustment, routing, overdelivery, basic, dates, manufacturing, execution, sequence, overview, process, confirmation, variance. , KBA , PP-SFC-EXE-CON , Confirmation , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.