SAP Knowledge Base Article - Public

3671239 - Some features in the Capacity Scheduling Board application appear to be disabled or not selectable.

Symptom

The Realign Schedules and Manage Operations buttons are grayed out in the Capacity Scheduling Board application.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Open the Capacity Scheduling Board application.
  2. Select respective AOR (Area of Responsibility).
  3. Provide the evaluation horizon.
  4. Select the work center.
  5. Observe that the buttons are disabled.

Cause

The Realign Schedules and Manage Operations buttons are available exclusively for bottleneck operations. 

Resolution

  • To enable the use of buttons, select the "Pacemaker Work Centers" option instead of the "All Work Centers" option.
  • Ensure that all prerequisites mentioned in the referenced KBA 3557362 "Issue with "Realign Schedules" and "Schedule Production" Buttons in Capacity Scheduling Board" is followed.

See Also

 Capacity Scheduling Board

Keywords

capacity scheduling board, options greyed out, buttons not enabling, drag and drop not working, pacemaker work centers, FTGL_DRAG_DROP, bottleneck operations, sap s/4hana cloud public edition, monitor work center schedule, production scheduling, realign schedules, schedule production , KBA , PP-CFS-GNT-2CL , Monitor Work Center Schedule Gantt view (Public Cloud) , PP-CFS-GNT , Monitor Work Center Schedule Gantt view , Problem

Product

SAP S/4HANA Cloud Public Edition all versions