SAP Knowledge Base Article - Public

3673407 - Title Ability to Change Settlement Rule for Co-Product Production Order After CFD2508.3 Symptom Previously, when settlement was completed for a co-product production order, it was not possible to change the settlement rule. Environment SAP S/4HANA

Symptom

Previously, when settlement was completed for a co-product production order, it was not possible to change the settlement rule.

Environment

SAP S/4HANA Cloud Public Edition

Cause

The original system behavior restricted changes to the settlement rule once the settlement process was done for co-product production orders.

Resolution

With the introduction of release CFD2508.3, the behavior has been updated:

  • If the cost has only been distributed (indicated by the presence of EBWP (WIP posting) but not EBVP (variance posting) on the item), it is now possible to change the settlement rule.

Keywords

Co-product production order, settlement rule, settlement changes, CFD2508.3, EBWP, EBVP, SAP S/4HANA Cloud Public Edition , KBA , CO-PC-OBJ-2CL , Cost Object Controlling (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions