Symptom

  • Cost Component Split (CCS) of Purchase Order Receipt is not functioning as expected.
  • Actual cost component fails to split during Goods Receipt (GR) for Purchase Order (PO). 
  • Need to know how to adjust the configuration to enable CCS breakdown. 

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Perform a Goods Receipt (GR) for a Purchase Order (PO).
  2. Observe that the actual cost component split does not occur as expected in the app "Material Price Analysis".

Cause

The configuration is related to SSCUI 104814 "Assign Condition Types to Origin Groups". 

If all entries of specific origin group are with ‘Valuation Variant’ values, the CCS breakdown will not work, because the entry with ‘Valuation Variant’ value will not be considered in the actual costing. The entry without ‘Valuation Variant’ value will be. 

Resolution

Verify the configuration in SSCUI 104814 - Assign Condition Types to Origin Groups.

Ensure there is an entry that the 'Valuation Variant' field is left blank for the relevant origin groups in SSCUI 104814.

For the 'Valuation View' field, use '1' for group view and '0' for legal view/leading ledger. If both are necessary, create two entries with '1' and '0' views, ensuring the 'Valuation Variant' field is blank. 

See Also

Refer to: KBA - 0003208563 - Cost Component Split data for GR of Purchase Order

Keywords

cost component split, goods receipt, purchase order, actual costing, sap s/4hana cloud public edition, cost component structure, valuation variant, origin group, SSCUI 104814, CKM3, procurement costs, material consumption accounts, configuration , KBA , CO-PC-ACT-2CL , Actual Costing (Public Cloud) , How To