Symptom

There are different factory calendars per plant and per work center. While creating / processing inspection lots, following message is triggered:

QA197 - The start date of the inspection is not a valid workday.

This message indicates that the plant level factory calendar is taken into account for the lot, and not the calendar for the work center.


Read more...

Environment

  • SAP ERP Central Component
  • SAP ERP
  • SAP Enhancement package for SAP ERP
  • SAP S/4HANA, on-premise
  • SAP S/4HANA Cloud Private Edition

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP S/4HANA Cloud Private Edition all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions

Keywords

QM-IM, QA 197, KAKO, KALID, t001w, fabkl, work day, weekend, holiday, factory_calendar_id, qals-paendterm,  qals-pastrterm, paendterm, pastrterm, QALS, End Date of Inspection in Local Time Zone, Start Date of Inspection in Local Time Zone , KBA , QM-IM , Quality Inspection , Problem