Symptom
Input product ABC has been confirmed with quantity X in supply/make task, and the task has been finished. In data source "Production Orders By Header Input Products", search corresponding production order DEF, for corresponding operation and product ABC, fulfilled quantity is X, open quantity is zero.
Now open production lot DEF, perform adjustment confirmation to deduct X quantity for product ABC against corresponding task. Check in data source "Production Orders By Header Input Products" again, for corresponding operation and product ABC, fulfilled quantity is zero, open quantity is also zero.
Why open quantity is still zero after adjustment confirmation?
*ABC represents product ID
*DEF represents production order/lot ID
*X represents quantity
Environment
SAP Business ByDesign
Cause
Once a supply/make task is finished, open quantity of all input products will become zero. No matter what adjustment confirmation is done in corresponding production lot, the number stay still as zero.
Therefore, data source "Production Orders By Header Input Products" shows zero open quantity as well.
Resolution
System standard behavior.
See Also
Keywords
production order, open quantity, adjustment confirmation, SCMPOHDRIPU01, data source, production lot, adjustment confirmation , KBA , AP-PE-ORD , Production Order , Problem
SAP Knowledge Base Article - Public