3682535 - Heuristic planning selects lower priority PPM for first planned order after planning time fence

Symptom

  • Heuristic selected PPM with the lower source priority to generate the first planned order to cover the open demand that is inside the Planning time fence.
  • Order should be created at the exact same time the Planning Time Fence ended, but it is created late.


Read more...

Environment

Production Planning and Detailed Scheduling

Product

SAP S/4HANA all versions ; SAP Supply Chain Management all versions ; SAP enhancement package for SAP Supply Chain Management all versions

Keywords

heuristic, PPM priority, planning time fence, incorrect PPM selection, source of supply, SAPAPO/RRP3, on-time delivery, lot-for-lot, late delivery scenario, PP/DS application , KBA , SCM-APO-PPS-HEU , Heuristics , SCM-APO-PPS-HEU-PP , PP Heuristics , Problem