Symptom
-
System does not allow adding additional service items while creating a Service Entry Sheet (SES).
-
Only the original service item from the Purchase Order is available for entry.
-
Attempting to add a new SES item results in multiple validation errors.
-
SES does not accept manually entered service lines that are not part of the Purchase Order.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
-
Create a Purchase Order with a single planned service item.
-
Go to “Manage Service Entry Sheets” and create a new SES for the same PO.
-
Try to add a new service item manually that is not part of the PO.
-
System triggers errors because mandatory reference data cannot be determined.
-
SES can only be created for the existing PO service item.
Cause
Standard system behaviour.
Resolution
- To enable adding additional SES service lines, create or update the Purchase Order to include a Limit Item with the setting “Unplanned Services Allowed.”
- Only limit items that support unplanned service entry.
- For planned service items, the SES can only contain the service lines predefined in the PO.
See Also
Keywords
service entry sheet, lean services, sap s/4hana public cloud, purchase order, service procurement, unplanned services, planned-service purchase order, limit item, additional service items, errors, blocked, mandatory information, service specifications, pricing, account assignment, performance period, limits, tolerances. , KBA , MM-PUR-SVC-SES-2CL , Service Entry Sheet for Service Procurement (Public Cloud) , Problem