Symptom

RITA migration process is in Status 4 Migration complete (pending verification) and needs to be changed to Status 5 (Active).

Environment

SAP S/4HANA Cloud Public Edition 2508 

Reproducing the Issue

  1. Enter Configuration Activity Activate Registration for Indirect Taxation Abroad - Maintain Tax Registration Countries/Regions - 103464 
  2. Check if status is set to 4. and verify that your data has been migrated correctly
  3. Set to status 5 is not possible manually

Cause

This steps needs to be completed by SAP.

Resolution

In case of development, test and production system activation, an incident needs to be raised for component FI-GL-GL-F-2CL. Development provides the necessary access to the CB user provided in the incident after confirming that the content of Note 2907372 is accepted by the customer. When access is granted, user can set status to 5.

In case the setting needs to be done in development, test and production system, one ticket is sufficient to be created in the production system.

However, if the ticket is raised via development or test system, a separate ticket needs to be raised for production as well.

See Also

Activating Registration for Indirect Taxation Abroad (RITA)

2907372 - UPDATE: Restriction Note for RITA in SAP S/4HANA CE2005 and further Releases: 'Registration for Indirect Taxation Abroad: Not supported Apps, Countries and Processes.' - SAP for Me

Keywords

RITA activation, status 4, status 5, Migration complete (pending verification) , KBA , FI-GL-GL-F-2CL , Value Added Tax (VAT) (Public Cloud) , How To