Symptom
- Start date of the SNP planned order is earlier than the availability date due to consideration of goods receipt (GR) processing time.
- Availability date is set as the date when the order is created in the key figure "Production (Planned)".
- GR processing time has been considered, which causes the order start date to be set in the past.
- User expectation is that the order start date to match the availability date and for GR processing time to be added to the order end date.
Read more...
Environment
- SAP Supply Chain Management
- SAP Advanced Planning and Optimization
- Supply Network Planning
Product
SAP Supply Chain Management all versions
Keywords
snp planned orders, goods receipt time, gr processing time, availability date, order start date, order end date, snp global profile, heuristic, optimizer, capacity leveling, manually creation. , KBA , SCM-APO-SNP-BF , Basic Functions , SCM-APO-SNP-CAP , Capacity Leveling , SCM-APO-SNP-HEU , SNP Heuristic Planning , Problem
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results
Visit SAP Support Portal's SAP Notes and KBA Search.
SAP Knowledge Base Article - Preview