Symptom
Dependent requirements are too high on the component level.
There is specific business requirement to prevent these dependent requirements from being planned by MRP.
Environment
- SAP S/4HANA Cloud Public Edition
Cause
Resolution
Go to material master, set field 'MRP relevancy for dependent requirements' in MRP view 4 to value '1'.