3692802 - How to exclude dependent requirements from being planned by MRP

Symptom

Dependent requirements are too high on the component level.
There is specific business requirement to prevent these dependent requirements from being planned by MRP. 

Environment

  • SAP S/4HANA Cloud Public Edition

Cause

Resolution

Go to material master, set field 'MRP relevancy for dependent requirements' in MRP view 4 to value '1'.