Symptom

In Monitor Stock / Requirements List app (MD04), different users see different Receipt/Requirements Dates for the same material and plant combination.

Environment

SAP S/4HANA Cloud Public Edition 

Cause

The 'Date of requirement/receipt' settings are maintained differently for different users under the "Dates" tab in the user settings of this app.

Resolution

  • Click on User Settings button on the top-right corner.
  • Maintain the same setting against 'Date of requirement/receipt' .