Symptom
There is no suitable budget maintained on a WBS element, for example the bottom level WBS element of the project. Need to know which budget control object will be considered for this WBS element.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Attempt to post on a WBS with no budget.
- Observe that the post is successfully done with/without triggering any error message.
- Need to know the logic of budget control object for this WBS.
Cause
If there is no suitable budget maintained on a WBS element, then WBS of its father or father's father or ..., where suitable budget is defined, will be considered as budget control object for the WBS element. The defined budget of the budget control object will be considered during budget checking.
Resolution
Check upper level WBS element within the same project to verify defined budget.
Keywords
budget check, budget control object, defined budget, project, WBS, no budget, sap s/4hana cloud public edition, budget availability control, error not triggered, upper level , KBA , CO-OM-CCA-AVC-2CL , Cost Center Budget Availability Control (Public Cloud) , CO-OM-PRO-AVC-2CL , Project Budget Availability Control (Public Cloud) , Bug Filed