Symptom
- An error was reported during an attempt to reverse actual settlements for specific WBS elements via the "Schedule Overhead Accounting" app using the "Actual Settlement: Projects (SAP)" template.
- The error message "An error occurred. Please create an incident on component CO-OM-OPA." was displayed.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Navigate to the "Schedule Overhead Accounting" app.
- Select the template "Actual Settlement: Projects (SAP)."
- The parameter should be entered, and the job should be executed
Cause
- Unfortunately, the actual error can only be verified in the backend system.
- A possible error message is: "Enter posting date in period XX."
- The error is caused by a conflict between the posting date and the posting period in the parameters when the job is scheduled.
Example:
Parameters:
- Posting Period: 010 (the last date of period 10.2025 is 30.11.2025)
- Fiscal Year: 2025
- Posting Date: 31.12.2025
In this case, the posting date 31.12.2025 is not considered valid for period 010.2025, and an error is issued.
Resolution
- First, the Posting Period, Fiscal Year, and Posting Date should be checked, and the data should be confirmed as correct.
- The last day of the period can be checked through the SSCUI "Maintain Fiscal Year Variants."
- Alternatively, settlement jobs can be scheduled without specifying a posting date; the posting date will be automatically derived as the last day of the posting period.
Keywords
CO-OM-OPA, Schedule Overhead Accounting, Actual Settlement , KBA , CO-OM-OPA-2CL , Overhead Orders (Public Cloud) , Problem
Product
SAP S/4HANA Cloud Public Edition all versions
SAP Knowledge Base Article - Public