Symptom
- Not able to create settlement rules for non billing WBS Elements in 'Project Planning' app post the 2602 CE upgrade.
- Previously created settlement rules for non billing WBS elements cannot be found in the 'Project Planning' app post the 2602 CE upgrade.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Open a project in the app 'Project Control - Enterprise Projects'.
- Navigate to a a WBS element which is not a billing element.
- Notice that it is not possible to view/create settlement rules.
Cause
Post the 2602 CE release the system design will not allow to create settlement rules for non billing WBS elements in the 'Project Planning' app.
Resolution
As a workaround:
- To create settlement rules for non billing elements: please use the app 'Maintain settlement rule for WBS Elements' to create settlement rules for WBS elements which not billing elements.
- To display existing settlement rules for non billing WBS elements the app 'Manage Settlement Rules - Projects' can be used.
Keywords
settlement rules, non billing element, WBS element, Project with revenue, Project Control - Enterprise Projects, Project Planning, Maintain settlement rules for WBS Elements, Manage settlement rules - Projects, SAP S/4HANA Cloud Public Edition, cannot create settlement rules, cannot display settlement rules, PPM-SCL-STR, PPM-SCL-STR-FIO. , KBA , PPM-SCL-STR , Project Structure (Public Cloud) , PPM-SCL-STR-FIO , Fiori UI for Project Structure (Public Cloud) , Problem