Symptom
Planning run ends with warning "There is already a scheduled execution not yet finished" and without any other result.
Environment
SAP Business ByDesign
Reproducing the Issue
- Navigate to work center Supply Planning, access view Planning Runs.
- Select planning run ABC.
- Open application log XYZ.
- Select the tab Results.
- Observe that there is only one warning message: "There is already a scheduled execution not yet finished".
*ABC represents planning run ID
*XYZ represents application log ID
Cause
When multiple jobs are executed simultaneously for a specific planning run, none of them can take effect. In the corresponding application logs, under the tab Results, there will be only one warning message: "There is already a scheduled execution not yet finished".
To validate this, select this planning run, click button View Jobs, select "Scheduled Jobs" in drop down list, usually there are multiple jobs scheduled at same date and time.
Resolution
Avoid schedule multiple jobs at totally same date and time for planning run.
See Also
Keywords
planning run, warning message, supply planning, application log, simultaneous jobs, planning run results, job scheduling, not yet finished, scheduled execution , KBA , AP-SDM-MRP , Material Requirements Planning , Problem