3716208 - Missing overhead in material cost estimate for new fiscal period

Symptom

  • Missing overhead for material cost estimate in test system for new fiscal period in 2026.
  • Error message: "Cost center xx is not defined within the validity period of this entry."

Environment

SAP S/4HANA Cloud Public Edition

Cause

  • The cost center xx referenced in the costing sheet credit line does not exist in the validity of cost estimate.

Resolution

Create the missing cost center 61ZQIGM001 in the test system or update the costing sheet to reference a valid cost center.

See Also

Keywords

missing overhead, material cost estimate, test system, fiscal period 2026, cost center validity, CK11N, costing sheet, SAP S/4HANA Cloud, public cloud, overhead calculation, cost element, plant BE03, PPC1, 61ZQIGM001. , KBA , CO-OM-OPA-2CL , Overhead Orders (Public Cloud) , Problem