Symptom
- Unable to change the "Processing Status" of WBS in a project despite the availability of a budget for the WBS.
- The "Processing Status" of the parent WBS differs from that of the child WBS.
- "Processing Status" Button is greyed out.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Navigate to "Project Control - Enterprise Project" and select the project.
- Select the project and click on the "Edit" option available at the header level.
- Choose "Edit In" and select "Project Planning".
- Attempt to change the "Processing Status"; the system does not allow the change.
Cause
This is the expected behavior by design.
Resolution
- Ensure that no other users are actively editing the project or that no draft is ongoing.
- Select the specific WBS line within the project.
- Once the WBS line is selected, the "Processing Status" button will be enabled.
- Proceed to change the "Processing Status" of the WBS.
- Verify the status change and confirm functionality.
Please note that button becomes enabled only when the WBS line is selected.