Symptom

After setting an order to TECO (Technically Completed), different dates may be recorded in the following fields:

  • AUFK-IDAT2

  • JCDS-UDATE for status I0045 (Technically Completed)

This can be observed especially in scenarios where the user time zone differs from the application server (system) time zone.

Even after implementing SAP Note 1252334, the date in AUFK-IDAT2 may reflect the user's local time, while JCDS-UDATE continues to reflect the system time.


Read more...

Environment

  • Controlling (CO)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP enhancement package for SAP ERP
  • SAP enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA Finance
  • SAP S/4HANA


Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Finance all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

TECO, technically completed, AUFK-IDAT2, JCDS-UDATE, I0045, time zone, user local time, system time, status change date, SAP Note 1252334, SAP Note 2760378, SAP Note 3156583 , KBA , CO-OM-OPA-A , Master Data , CO-OM , Overhead Cost Controlling , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.