Symptom
It is not possible to trigger new hire tasks in a sequence. For example: Only when the buddy task is completed, the meeting task is generated.
Environment
SAP SuccessFactors Onboarding
Cause
Product behavior.
Resolution
- Tasks appear in parallel by design.
- This means that when the Primary new hire tasks stage is reached, all primary new hire tasks will trigger as per the onboarding program.
- Workaround could be to separate the tasks by primary and secondary, having the secondary tasks trigger after the primary tasks in the process variant.
-
Enhancement requests can be submitted following KBA 2090228.
See Also
KBA 2090228 - How to submit enhancement ideas for SAP SuccessFactors Products
Keywords
tasks, sequential tasks, task dependencies, parallel tasks, dependency control, sequence-based logic, by design, product limitation, task order, workflow sequence, offboarding tasks, configuration limitation, order , KBA , LOD-SF-OBX-NHA , New Hire Activities (activities, tasks, buddy, equipment) , LOD-SF-OBX-OFT , OFB Tasks , Problem