Symptom
-
In production or process orders (e.g. created via CO01 / COR1), inconsistencies are observed in:
-
Basic start and end dates
-
Scheduled dates
-
Operation start and finish dates
-
-
Example symptoms include:
-
Operation sequence appears inconsistent (e.g. operation 0010 starts after operation 0020)
-
Dates change automatically after pressing Enter during order creation
-
Small changes in order quantity lead to different scheduling results
-
Start/finish dates do not follow the expected routing sequence
-
Read more...
Environment
- SAP ERP Capacity Planning (PP-CRP)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
- SAP S/4HANA Cloud Private Edition
Product
Keywords
inconsistent date, factory calendar, basic dates, scheduled dates, operation dated, end date, start date, processing, setup, labor, formula , KBA , PP-CRP-SCH , Scheduling , Problem
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results
Visit SAP Support Portal's SAP Notes and KBA Search.
SAP Knowledge Base Article - Preview