3730538 - Common Causes for Date Inconsistencies in Production and Process Order Scheduling

Symptom

  • In production or process orders (e.g. created via CO01 / COR1), inconsistencies are observed in:

    • Basic start and end dates

    • Scheduled dates

    • Operation start and finish dates

  • Example symptoms include:

    • Operation sequence appears inconsistent (e.g. operation 0010 starts after operation 0020)

    • Dates change automatically after pressing Enter during order creation

    • Small changes in order quantity lead to different scheduling results

    • Start/finish dates do not follow the expected routing sequence


Read more...

Environment

  • SAP ERP Capacity Planning (PP-CRP)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP Enhancement package for SAP ERP
  • SAP Enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA, on-premise
  • SAP S/4HANA Cloud Private Edition

Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Cloud Private Edition all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

inconsistent date, factory calendar, basic dates, scheduled dates, operation dated, end date, start date, processing, setup, labor, formula , KBA , PP-CRP-SCH , Scheduling , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).