Symptom
The basic start and end dates in the production order do not align with the expected operation duration. Given the set duration and dates within the operation, the end dates should be earlier.
Read more...
Environment
- SAP ERP Production Planning (PP)
- SAP ERP All versions
- SAP ERP Central Component All versions
- SAP R/3 All versions
- SAP R/3 Enterprise All versions
- SAP S/4HANA All versions
- SAP S/4HANA Cloud Private Edition All versions
- SAP enhancement package for SAP ERP All versions
- SAP enhancement package for SAP ERP, version for SAP HANA All versions
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Cloud Private Edition all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions
Keywords
production order, scheduling margin key, float, operation duration, basic start date, basic end date, ERP Production Planning, ERP Central Component, R/3, S/4HANA, scheduling issue, operation delay, workday delay, scheduling configuration, production scheduling , KBA , PP-CRP-SCH , Scheduling , Problem