3730714 - Plan Activity not filled in KP26 after SAC retraction when unexpected VMSL data exists in ACDOCP

Symptom

After plan data is retracted from SAP Analytics Cloud (SAC) into SAP S/4HANA and transferred from ACDOCP to classic CO planning tables, Plan Activity is not available in KP26 for direct production cost centers.

This can lead to issues during tariff calculation in KSPI, even when the activity type master data is maintained with a plan price indicator based on capacity.

The issue is typically observed in a scenario where:

  • Valuation Quantity (VMSL) is used for scheduled / plan activity-related quantity
  • Reference Quantity (RMSL) is used for capacity-related quantity
  • transfer to classic CO tables is performed using reports such as:
    • R_FINS_PLAN_TRANS_ACTOUT_2_ERP
    • R_FINS_PLAN_TRANS_CO_S4H_2_ERP


Read more...

Environment

  • Controlling (CO)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP enhancement package for SAP ERP
  • SAP enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA Finance
  • SAP S/4HANA


Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Finance all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

SAC retraction, ACDOCP, KP26, KSPI, plan activity missing, capacity quantity, VMSL, RMSL, LST, R_FINS_PLAN_TRANS_ACTOUT_2_ERP, R_FINS_PLAN_TRANS_CO_S4H_2_ERP, tariff calculation, direct production cost center , KBA , CO-FIO-OM-PL , Planning , CO-OM , Overhead Cost Controlling , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.