3733443 - PO Price does not match awarded Supplier Quotation price from Ariba

Symptom

  • A Purchase Requisition (PR) is created with a specific net value.

  • An RFQ is generated from the PR and sent to SAP Ariba Sourcing.

  • The bidding process is completed, and the quotation is awarded to a supplier for a lower or different amount than the original PR.

  • The awarded supplier quotation is successfully transferred back to SAP S/4HANA.

  • However, when the follow-on Purchase Order (PO) is created, it retains the original net price from the Purchase Requisition instead of adopting the awarded quotation price.


Read more...

Environment

SAP S/4HANA Cloud Public Edition

Product

SAP S/4HANA Cloud Public Edition all versions

Keywords

purchase requisition price, po price not updated, quotation price not adopted, rfq ariba integration, po uses pr net price, s/4hana cloud public edition, mm_pur_s4_pr_modify_item, rfq to po, supplier quotation transfer, manage purchase order app, operational procurement, net price override, pricing conflict pr vs quotation, purchase order pricing, ariba sourcing quotation , KBA , MM-PUR-RFQ-2CL , RFQ/Quotation (Public Cloud) , Problem