Symptom
Navigating to the app "Production Cost Summarization - Event-Based (F7311)", notice the 'Plan Quantity' is doubled.
Environment
SAP S/4HANA Cloud Public Edition
Cause
There is a known coding issue.
Resolution
The fix is planned with feature update 2602.2, planned release date 16.04.2026.
See Also
Keywords
production cost summarization, event-based, f7311, plan quantity doubled, planned cost doubled, planned vs actual, production accounting report, cost report discrepancy, plan cost double, event-based production, reporting public cloud, s4hana cloud public edition, cost variance display, production cost report, double counting , KBA , CO-FIO-OBJ-IS-2CL , Reporting (Public Cloud) , Problem