Symptom
Although "Start in the Past" field is maintained in configuration activity 101173 - Define Scheduling Parameters for Planned Orders, MRP still cannot generate planned orders in the past.
Read more...
Environment
SAP S/4HANA Cloud Public Edition
Product
SAP S/4HANA Cloud Public Edition all versions
Keywords
start in the past, planned orders, MRP, public cloud, scheduling parameters for planned orders, configuration activity 101173, backward scheduling, dates in future, plant parameters, oppr, oppq, opu5 , KBA , PP-MRP-2CL , Material Requirements Planning (Public Cloud) , Problem