3740848 - Cannot Change Responsible Cost Center of WBS Element After Financial Plan Data Upload

Symptom

The cost center cannot be changed in the WBS element after financial plan data has been uploaded.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Create a WBS element.
  2. Import budget data via the Budget Data app and upload it to the WBS element.
  3. Open Enterprise Project Management and click on Project Planning.
  4. Try to adjust the cost center of the WBS element.

Cause

The system works as designed: after a project is created, the company code cannot be edited; and once there are postings (for example, financial plan data) on a project or WBS element, the responsible cost center can no longer be changed.

Resolution

Once a project is created it is no longer possible to edit the Company Code. Then once there are postings on a WBS/Project it is no longer possible to edit the Cost Center.
As this is the current standard behavior please consider voting on Improvement Request https://influence.sap.com/sap/ino/#/idea/329790 if you would like to see this behavior changed in future releases.

Keywords

responsible cost center, wbs element, cannot change cost center, cost center change blocked, project planning app, budget data app, financial plan data, postings exist, by design, project management, enterprise project management, public cloud, cost center edit, wbs master data, s/4hana cloud , KBA , PPM-SCL-STR , Project Structure (Public Cloud) , How To