3740848 - Cannot change Responsible Cost Center of WBS Element after financial plan data upload

Symptom

The responsible cost center cannot be changed in the WBS element after financial plan data has been uploaded.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Create a WBS element.
  2. Import budget data via the "Import Financial Plan Data" app and upload it to the WBS element.
  3. Navigate to the project or WBS element in the "Project Control - Enterprise Projects" app or in the "Project Planning" app.
  4. Try to adjust the responsible cost center of the WBS element, while the field is non-editable.

Cause

The system works as designed: after a project is created, the company code cannot be edited; and once there are financial plan data on the project or WBS element, the responsible cost center can no longer be changed.

Resolution

As this is the current standard behavior, consider voting on Improvement Request https://influence.sap.com/sap/ino/#/idea/329790 to see this behavior potentially changed in future releases.

Keywords

responsible cost center, wbs element, cannot change cost center, cost center change blocked, cost center, project planning app, budget data app, financial plan data, postings exist, by design, project management, enterprise project management, public cloud, cost center edit, wbs master data, s/4hana cloud , KBA , PPM-SCL-STR , Project Structure (Public Cloud) , How To