3748749 - Manage Multilevel Bill of Material cannot explode subassembly due to time zone date shift; selected date moves back one day - sap s/4hana cloud public edition

Symptom

APP Manage Multilevel Bill of Material could not explode successfully due to time zone issue; selected date moves back by one day and the app shows “No components exist for this subassembly”.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Open app Manage Multilevel Bill of Material (Fiori ID F5238) and search for the required BOM.
  2. Select the BOM line to open the detail screen; initially, the components table is empty.
  3. Open Timeline: Change Number, then choose Select; the components and subassembly appear.
  4. Click the chevron to expand the subassembly.
  5. Observe that the selected date shifts back by one day and the expansion fails with the message “No components exist for this subassembly”.

Cause

Resolution

The issue will be fixed on 06/11/2026.

Keywords

Manage Multilevel Bill of Material, F5238, subassembly, explode, explosion failure, time zone, timezone, date shift, selected date moved back, “No components exist for this subassembly”, BOM, multilevel, change number, timeline, validity date , KBA , LO-MD-BOM-2CL , Bills of Material (Public Cloud) , Problem