Symptom
Warning message FCO_AVC_PS220: Account &1 isn't assigned to semantic tag PSQBUDGET raised when uploading budget, even if the semantic tag is already assigned correctly.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Open the app Import Financial Plan Data.
- Upload budget import file with entries posted to GL account assigned to semantic tag PSQBUDGET.
- Observe the error: "Account &1 isn't assigned to semantic tag PSQBUDGET."
Cause
PSQBUDGET is a special parent semantic tag and is not intended to be assigned directly to G/L accounts. PSQBUDGET serves as the parent semantic tag for ACT_COST and PRSLS_STCK. The budget control-related accounts are not those directly assigned to PSQBUDGET, but rather the accounts assigned to its child semantic tags, such as ACT_COST and PRSLS_STCK.
Resolution
If the budget control profile used by the project is using tag PSQBUDGET, do not assign PSQBUDGET directly to G/L accounts:
- Assign P-accounts (primary cost/revenue) to ACT_COST.
- Assign X-accounts (balance sheet) to PRSLS_STCK.
- If neither applies, create a suitable semantic tag and set PSQBUDGET as its parent, then assign the account to that tag.
Then, replicate changes so they take effect: Use the app Replicate Runtime Hierarchy after saving the FSV and semantic tag assignments and replicate the FSV YPS2.
See Also
Keywords
PSQBUDGET, ACT_COST, PRSLS_STCK, YPS2 FSV, BAL FSV, import financial plan data, budget availability control, project budget, semantic tag mapping, warning account isn't assigned, replicate runtime hierarchy, AVC, financial statement version, plan data import, budget upload error, FCO_AVC_PS220 , KBA , CO-OM-CCA-AVC-2CL , Cost Center Budget Availability Control (Public Cloud) , Problem