Symptom
Under the Milestones tab within the "WBS Element" app, it is not possible to edit the "Used for Billing" option against the milestone.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Open the project in the "Project Control - Enterprise Projects" app
- Navigate to the "Project Planning" app, switch to edit mode.
- Open the relevant WBS element.
- Create a milestone.
- Attempt to change the "Used for Billing" option from "No" to "Yes".
- Observe the field is read-only.
Cause
The "Used for Billing" column in WBS milestones is read-only by design. It only indicates whether the milestone is referenced in a sales order billing plan. "No" means the milestone has not been used in a billing plan within a sales order.
Resolution
Use the "Manage Sales Orders - Version 2" app to link the project milestone to billing plan items, then return to "Project Planning" app and verify that the WBS milestone shows "Used for Billing" as "Yes" now.
See Also
- SAP Help Portal - WBS Element | SAP Help Portal
- KBA 3656020 - Unable to link Project Milestones to Billing Plan Items via API or SAPGUI apps
Keywords
used for billing, wbs, milestone, milestones, project planning, billing plan, read-only field, enterprise project, milestone billing, public cloud, s/4hana cloud, project management, wbs element, unable, tick , KBA , PPM-SCL-STR-FIO , Fiori UI for Project Structure (Public Cloud) , SD-BIL-IV-BP-2CL , Billing Plan (Public Cloud) , Problem