SAP Knowledge Base Article - Public

3752029 - Stock Transport Order between different WBS Elements - SAP S/4HANA Cloud Public Edition

Symptom

It is not possible to create a Stock Transport Order to transfer the goods between two different WBS Elements. 

Environment

SAP S/4HANA Cloud Public Edition

Cause

With a Stock Transport Order, project stock can be transferred between plants only when it remains assigned to the same WBS element. Issuing stock from one WBS element and receiving it into a different WBS element is not supported. In short, STOs allow movement of the same project stock between plants, but do not permit changing the WBS element during the transfer.

Resolution

Using the Post Goods Movement app, a transfer posting with movement type 415 Q enables transferring project stock between two different WBS elements (i.e., different projects).

Keywords

transfer, WBS, element, STO, company code, cross-company, different WBS, Intra STO, WBS element, WBS , KBA , MM-IM-ST-PO-2CL , Stock Transfer for Stock Transport Orders (Public Cloud) , Problem

Product

SAP S/4HANA Cloud Public Edition all versions