Symptom

When user navigates to curriculum details page assignments tab, required date information shown has text "Days" which is not getting translated as per user's locale preference.

Environment

SAP SuccessFactors Learning

Reproducing the Issue

  1. Login into BizX
  2. Navigate to Learning
  3. Activities menu (top right corner) -> select Curricula
  4. Go to any curriculum details 
  5. Go to Assignments tab and check text associated with required date information.
  • In English it is shown as " Required every 60 Days "
  • In Norwegian it is shown as "Påkrevd hver 60 Days "
  • In German it is shown as "Erforderlich alle 60 Days "

In all languages "Days" text is not getting translated. 

Resolution

Engineering team has found code fix required to resolve the defect. This defect will be fixed in 2H 2026 release.

Keywords

sf, learning, curriculum, days, redesigned experience, assignments, KI1H2026  , KBA , LOD-SF-LMS-CUR , Curricula , Known Error

Product

SAP SuccessFactors Learning 2605