Symptom
- In strategy-based maintenance plans configured with scheduling type Fixed Date, call dates for long cycles (for example, 10 years and above) progressively shift by months instead of keeping the same day/month.
- Initial calls may be correct, but later calls move from the expected key date (for example, from 05.01.YYYY to 05.02.YYYY, then 05.03.YYYY), showing a cumulative drift.
Read more...
Environment
- SAP ERP Plant Maintenance (PM)
- SAP ERP Customer Service (CS)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
- SAP S/4HANA Cloud Private Edition
Product
SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Cloud Private Edition all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions
Keywords
fixed date, fixed-date scheduling, maintenance plan, preventive maintenance, strategy-based, ip10, ip11, long cycle, 10 years, date drift, date shift, strategy unit, mon, yr, scheduling alignment , KBA , PM-PRM-MP , Maintenance Plans , Problem