Symptom
When running finite heuristic the available projected inventory (stock) is not used, instead new receipts are created on a difference source of supply, for example:
Product 1 LocationA – demand = 100
LocationSourceX – Projected inventory = 100
LocationSourceY – Projected inventory = 0
Instead of using the projected inventory available at LocationSourceX to supply locationA, new receipts are created on LocationSourceY.
Read more...
Environment
• SAP Supply Chain Management (SCM)
• SAP Integrated Business Planning (SCM-IBP)
Keywords
STK, component, PDS, plant, loc, FH, OBP, order, surplus. , KBA , SCM-IBP-RM-FH , Order-Based Finite Heuristic , SCM-IBP-RM-PLG , Planning , Problem