Symptom
The delayed execution in our process changed by one hour due to the winter & summer time change in our time zone.
Environment
- Product: SAP Signavio Process Governance
- Approval Workflow for SAP Signavio
Reproducing the Issue
- Configure a workflow step that waits a fixed duration (for example, 10 days) after the previous task ends.
- Ensure the waiting period spans a daylight saving time switch from winter to summer time
- Observe that the created task starts one hour later than the expected local time
Resolution
The system processes and schedules internally in UTC. When a fixed wait duration crosses a daylight saving time change, the resulting local start time can shift by one hour.
Keywords
daylight saving time, dst, summer time, winter time, utc, time zone, workflow task, wait duration, pause step, scheduling offset, one hour delay, start time shift, process governance tasks, scheduled task timing, local time discrepancy, sap signavio, process governance , KBA , BPI-SIG-PG-EDT , Process Governance Editor , Problem