Symptom
After running the production planning with T-Code /SAPAPO/CDPSB0(Heuristic SAP_MRP_001), the system creates only 500 planned orders. Which do not fulfill the total demands.
Read more...
Environment
- SAP Supply Chain Management
- SAP Advanced Planning and Optimization
Product
SAP S/4HANA Cloud Private Edition all versions
Keywords
/sapapo/cdpsb0, /sapapo/rrp3, pp/ds, eppds, planned order limit, only 500 orders, production planning run, pp heuristics, heuristic, order creation cap, demand not fulfilled, planning profile, order creation, ppds planning , KBA , SCM-APO-PPS-HEU-PP , PP Heuristics , Problem
About this page
This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).Search for additional results
Visit SAP Support Portal's SAP Notes and KBA Search.