3772903 - With Strategy Group 11 (gross requirements planning) MRP creates Purchase Requisition only for remaining quantity, instead of full quantity with already existing receipts.

Symptom

  • Master data uses strategy group 11 – make-to-stock production/gross requirements planning.
  • A planned independent requirement (PIR) is created for quantity 25 (for example).
  • A fixed receipt exists as supply for quantity 20 (for example).
  • After MRP run (MRP Live), the system creates a purchase requisition (PR) for only 5 instead of 25.


Read more...

Environment

  • SAP S/4HANA
  • Material Requirements Planning

Product

SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Cloud Private Edition all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

mrp live, md01n, md04p, strategy 11, gross requirements planning, pir, planned independent requirements, purchase requisition, pr quantity, stock transfer order, existing supply, lot sizing ex, rescheduling, mrp area, mrp result , KBA , PP-MRP , Material Requirements Planning , Problem