Symptom
When running MRP in transaction MD02 with scheduling option 2 (Lead Time Scheduling and Capacity Planning), the system creates planned orders on dates where the assigned work center already has capacity overload.
The expectation is that the system should consider the existing capacity load and schedule the planned orders on dates with available capacity. However, the planned orders are still generated on overloaded dates.
Read more...
Environment
- SAP ERP Capacity Planning (PP-CRP)
- SAP R/3
- SAP R/3 Enterprise
- SAP ERP Central Component
- SAP ERP
- SAP Enhancement package for SAP ERP
- SAP Enhancement package for SAP ERP, version for SAP HANA
- SAP S/4HANA, on-premise
- SAP S/4HANA Cloud Private Edition
Product
Keywords
MD02, scheduling 2, lead time scheduling, capacity planning, infinite capacity, work center overload, planned order not created, component PR created, purchase requisition, MRP, capacity leveling, CM21, CM25, PP, CRP , KBA , PP-CRP-SCH , Scheduling , Problem