Symptom
After changing the responsible cost center on a released WBS element, the asset under construction (AuC) master record still shows the original cost center.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Release an investment project/WBS element so that an AuC is created automatically.
- Post initial costs and run the first event-based settlement to the AuC.
- Change the responsible cost center on the WBS element.
- Post additional costs and run subsequent event-based settlements.
- Open the AuC in the Manage Fixed Assets app and observe that the cost center remains the original value and the field is display-only.
Resolution
Once the AuC has been created, its cost center will not be updated to reflect later changes in the WBS master data.
Keywords
auc, asset under construction, cost center, wbs element, cost center change, not updated, synchronization, event-based settlement, manage fixed assets, master data, project control, enterprise projects, public cloud, s/4hana cloud, display-only field , KBA , FI-AA-AA-A-2CL , Master Data (Public Cloud) , How To