Symptom
In the application "Change Production Order" (transaction CO02), when a production order is rescheduled, the system uses the dates of already confirmed operations as the basis for scheduling subsequent operations.
Read more...
Environment
SAP S/4HANA Cloud Public Edition
Product
Keywords
confirmed operations, scheduled dates overwritten, actual confirmation dates, rescheduling, production order, order scheduling, CO11N, manage work center capacity, finally confirmed operations, operation dates, baseline plan, scheduling anchor, subsequent operations, discrete manufacturing, planning dates , KBA , PP-SFC-EXE-2CL , Order Execution (Public Cloud) , PP-CRP-SCH-2CL , Scheduling (Public Cloud) , PP-SFC-EXE , Order Execution , PP-CRP-SCH , Scheduling , Problem