3779108 - RKANBU01 runs for a long time when a WBS element is entered in the Project field

Symptom

When executing report RKANBU01 to correct commitment inconsistencies, the report runs for a long time or does not finish within the expected runtime.

The issue can occur although the user intends to restrict the report to one specific WBS element or a small number of objects.

In runtime analysis, the report may show that a large number of purchase order items are processed.


Read more...

Environment

  • Controlling (CO)
  • SAP R/3
  • SAP R/3 Enterprise
  • SAP ERP Central Component
  • SAP ERP
  • SAP enhancement package for SAP ERP
  • SAP enhancement package for SAP ERP, version for SAP HANA
  • SAP S/4HANA Finance
  • SAP S/4HANA


Product

SAP ERP Central Component all versions ; SAP ERP all versions ; SAP R/3 Enterprise all versions ; SAP R/3 all versions ; SAP S/4HANA Finance all versions ; SAP S/4HANA all versions ; SAP enhancement package for SAP ERP all versions ; SAP enhancement package for SAP ERP, version for SAP HANA all versions

Keywords

RKANBU01, commitment inconsistency, commitment correction, correction report, WBS element, Project field, Project Definition, PROJ-PSPID, PRPS-POSID, long runtime, performance, purchase order items, COOI, EKPO, SAP Note 1746429, SAP Note 152571 , KBA , CO-OM-OPA-D , Commitments , CO-OM , Overhead Cost Controlling , Problem

About this page

This is a preview of a SAP Knowledge Base Article. Click more to access the full version on SAP for Me (Login required).

Search for additional results

Visit SAP Support Portal's SAP Notes and KBA Search.