Symptom
After the conversion of a project demand into a purchase requisition, the supplier assigned to the demand in the "Manage Project Demand" app is not carried over as the source of supply in the purchase requisition item.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Create a demand in "Manage Project Demand" app, assign a supplier to the demand, and request the demand
- Open the app "Manage Project Procurement" app and navigate to the relevant PR item
- Add the Supplier column, and observe that the supplier assigned in the project demand is displayed
- Open the same PR item in "Manage Purchase Requisitions" app and notice that the Source of Supply tab is empty
- Open the same PR item in "Process Purchase Requisitions" app, and notice that the Assign Source of Supply button is available
Cause
When a project demand includes a supplier and is converted to a purchase requisition, the supplier is transferred as the Desired Supplier only. It is not an Assigned Source of Supply by design.
Resolution
Assign the Source of Supply explicitly in the Purchase Requisition.
Keywords
manage project procurement, project demand, supplier, desired supplier, source of supply, purchase requisition, purchase requisition item, manage purchase requisitions, process purchase requisitions, supplier not assigned, assigned, procurement, carryover supplier, assign source of supply , KBA , PPM-SCL-DMN , Project Demand (Public Cloud) , MM-FIO-PUR-REQ-SOC , Fiori UI for Sourcing Purchase Requisitions , Problem
SAP Knowledge Base Article - Public