Symptom
- A bank credit advice shows an open payment amount.
- The remaining amount can be seen on payment monitor, but when navigating to the customer account or creating a new bank payment advice, the expected payment item is not visible.
Environment
SAP Business ByDesign
Reproducing the Issue
- Navigate to the Receivables work center.
- Go to the Customer Accounts view.
- View the relevant customer account.
- In Open Items, search for the related bank credit advice or payment reference; the expected payment item is not found even though the bank credit advice shows a remaining amount in the Payment Monitor.
Cause
The remaining amount was cleared by a subsequent clearing document posted after the bank credit advice was created, so the Payment Monitor still shows a remaining amount while the customer account item is already fully cleared.
To verify this:
- Go to Payment Management work center.
- Open Payment Monitor view and locate the bank credit advice; note the displayed remaining amount and the timestamps.
- Open Receivables work center and view Customer Accounts.
- Navigate to Open Item and select All Items and search by the related payment reference.
- Notice that clearing documents posted after the bank credit advice creation have fully cleared the amount.
Resolution
System is working as expected.