Symptom
- Clarification needed on the activation of Scope Item 33Q (Actual Costing) in the live SAP system.
- Need for prerequisites, dependencies, or risks before proceeding with activation.
Environment
SAP S/4HANA Cloud Public Edition
Resolution
To ensure smooth activation of 33Q , check that following customizing is complete :
- All valuation classes used in existing Material master are mapped to GL in GBB/VBR (consumption account mapping via configuration 'Automatic Account Determination' (SSCUI 100297)).
- All GBB/VBR GL accounts are mapped to cost component structure via configuration 'Define Cost Component Structure' (SSCUI 102427).
- It's not prohibited but price determination should be changed to 3 (multi level) in MM after scope item 33Q actual costing activation.
Keywords
33Q, scope item 33Q, actual costing, activation, live system, sscui 100297, sscui 1024273, gbb/vbr, consumption account determination, cost component structure, price determination 3, multilevel, inventory accounting, public cloud, SAP s/4hana cloud public edition, activate 33Q, prerequisites , KBA , CO-PC-ACT-2CL , Actual Costing (Public Cloud) , Bug Filed
Product
SAP S/4HANA Cloud Public Edition all versions