Symptom
- No application log file is generated when uploading the project budget for the first time using the template.
- Also other apps like Project Budget Report don't store details of initial budget import.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Import Financial Plan Data
- Import initial budget.
- System informs that the plan data is successfully imported
- No log file with initial budget details exists
Cause
The current standard behavior does not create or store an application log or budget document for the initial/original project budget upload.
Resolution
- To suggest a new feature in the future, an improvement request can be submitted through SAP Customer Influence. This platform allows users to submit enhancement requests and vote on existing ideas.
- The ideas and voting results help SAP identify the product improvements and innovations that are most in demand, enabling them to prioritize future developments and releases accordingly.
See Also
KBA 2963059 - How to Submit Feature Requests for SAP S/4HANA Cloud Public Edition
Keywords
initial budget, application log, manage budget documents, import financial plan data, project budgeting template, original budget, no log generated, project budget report, review customer projects, display financial plan data, supplement, transfer, return, s/4hana cloud public edition, ppm-scl-str , KBA , PPM-SCL-STR , Project Structure (Public Cloud) , CO-FIO-OM-PL , Planning , Problem