3786908 - New Work Agreement ID Not Available For Resource Assignment In Plan Customer Projects

Symptom

New work agreement not available for resource assignment customer project.

Environment

SAP S/4HANA Cloud Public Edition

Reproducing the Issue

  1. Open the Plan Customer Projects app and respective project.
  2. Go to the Teams tab.
  3. Add a new resource and search for the user.
  4. Observe that the user is not searchable.

Cause

The cost center from the employee’s new work agreement is not assigned to the Service Organization used by the project.

Resolution

  1. Open the Manage Service Organizations app.
  2. Find and open the Service Organization assigned to the project.
  3. Review the Cost Centers assigned to this Service Organization.
  4. Verify whether the employee’s current cost center (from the new work agreement) is missing.
  5. If missing, assign the employee’s current cost center to the Service Organization and save.
  6. Return to Plan Customer Projects and repeat the resource search on the Teams tab.

See Also

SAP KBA 2817185 - Resource not shown in the available resources list in the Plan Customer Projects app

Keywords

plan customer projects, team tab, resource not shown, resource search, work agreement, new work agreement, service organization, cost center assignment, staffing, project staffing, available resources list, professional services, employee assignment , KBA , CA-CPD-SS , S/4HANA Public Cloud – Professional Service Projects , Problem