Symptom
- An error is raised when it is attempted to create a new Change Project.
- Error: Initial load for one of the active services is required
Environment
SAP Sales Cloud and SAP Service Cloud Version 2
Reproducing the Issue
- Login to Source system
- Go to System Settings
- Under Change Project settings go to Change Project View
- Click on + and create a new Change Project
- Click Save
- Error: Initial load for one of the active services is required is raised
Cause
- The initial load has not been performed for any service.
- An initial load of atleast one service is required before creating a new change projects to transport new changes.
Resolution
- Login to the Source system
- Go to System Settings
- Under Change Project view go to Registered Services
- Run an initial load for at least one service for which you plan to transport changes.
- Go to Change Projects view
- Publish and Transport the initial load to Target system
- Login to the Target system
- Go to System Settings
- Under Change Project settings go to Change Project view
- Publish the transported Initial load
- You can now login back to Source system and create a new Change Project
See Also
Refer to: Change Projects and Initial Load Overview
KBA: 3754206 - Error "Define the target system for the current landscape to start initial load" in change project registered services
Keywords
transport, page layouts, auto flows, change project, initial load, migration blocked, development to quality, sales & Service cloud v2, configuration transport, service initial load required, blocked transport, deployment, tenant to tenant, change projects, configuration copy, active services , KBA , CEC-CRM-CHP , Change Project for SAP Sales/Service Cloud , How To
Product
SAP Sales Cloud and SAP Service Cloud Version 2 all versions