Symptom
- A WBS element in an Investment Project shows an investment profile assigned (visible on the Control tab → Investment section), but the "Asset Under Construction ID" field is blank.
- AuC is created and appears in the above field. However, errors such as KD205 - "Maintain settlement rule for sender" and FINS_IM_EVENTBASED 002 – "No asset under construction assigned to WBS element" occurs when performing postings and settlements related to the WBS element.
Environment
SAP S/4HANA Cloud Public Edition
Reproducing the Issue
- Post costs to an existing investment WBS element that has an investment profile assigned but no AuC.
- Observe the error: "No asset under construction assigned to WBS element".
- Alternatively, perform settlement for this WBS via app Run Settlement
- Observe error "Maintain settlement rule for sender" in the application job log for the settlement run.
Cause
The AuC is not properly created/assigned for the affected WBS Element.
Resolution
- Remove the assigned investment profile from the affected WBS element and then re-add it again. This action triggers creation/assignment of the missing AuC for the WBS Element.
- After the AuC is created, retry the cost posting.
See Also
KBA 3047734 - Error KD205 "Maintain Settlement rule for Sender" occurs during settlement in APP Run Settlement - Projects(Collective)
Keywords
investment wbs, auc, asset under construction, auc not created, auc not generated, auc missing, investment profile, investment measure, wbs element, project system, api migration, migration cockpit, migrate your data, ps_project_maintain_srv, investment profile assigned after release, feature toggle, fco_abr_invma_eb_settle_auc, ce2602, kd205, kd574, settlement rule, project control enterprise projects, mass changes to project, f3891, remove investment profile, reassign investment profile, invma, fins_im_eventbased, 002 , KBA , IM-FA-2CL , Spec. investments (Public Cloud) , Problem
SAP Knowledge Base Article - Public