Symptom
After running the location heuristic, there is no SNP Planned orders generated beyond a certain month (for example, after January of the next year).
The Production (Planned) key figure shows no values beyond that month.
Read more...
Environment
- Supply Chain Planning and Optimization
- Supply Network Planning
- Heuristic
Product
SAP Supply Chain Management 7.0
Keywords
SNP heuristic, production not created, backlog remains, planning horizon, time bucket profile, production planned key figure, source of supply, ppm, validity period, plan not generated, future date, horizon extension, missing production. , KBA , SCM-APO-SNP-INS , Interactive SNP , Problem